Cellular Confinement Systems for Subgrade Stabilization — Standard Construction Procedure
Cellular Confinement Systems for Subgrade Stabilization — Standard Construction Procedure
1. Subgrade Preparation
- Clear the construction zone: remove weeds, mud, organic debris and loose topsoil.
- Level and compact the natural subsoil to meet specified compaction requirement.
- Inspect slope gradient, elevation and flatness; handle local soft spots by replacement or consolidation.
- Lay non-woven geotextile as separation layer to prevent intermixing of subsoil and upper aggregate. Overlap adjacent geotextile rolls by 15–20 cm.
2. Unfolding and Anchoring CCS
- Transport folded cellular confinement systems to position and unfold fully.
- Stretch the CCS tightly to reach the designed cell dimension and eliminate slack.
- Fix the panels with U-shaped steel anchor nails. Increase anchoring density at edges, joints and transition zones.
- Connect adjacent CCS modules with special locking fasteners as required.
- For highway expansion projects (old-new subgrade splicing), arrange CCS in transverse layout across the splicing interface.
3. Filling and Layered Compaction
- Fill graded crushed stone or aggregate into honeycomb cells. Do not exceed the height of the cell sheet.
- Fill evenly from the middle to both sides to avoid unilateral displacement of CCS panels.
- Compact fillers layer by layer using vibratory compaction equipment. Avoid heavy direct impact on welding seams.
- Check flatness and compaction degree after compaction. Supplement filling for partially empty cells.
4. Inspection and Supplementary Treatment
- Examine anchoring firmness, cell opening status and filling compactness.
- Repair local damaged sheets and reinforce loosely anchored positions.
- Remove excess scattered aggregate on the CCS surface.
5. Construction of Upper Pavement Structure
- After acceptance of the CCS composite cushion, construct the road base course and surface layer in sequence.
- Control rolling speed during upper-layer construction to prevent shifting of the CCS mattress.