Fiberglass Geogrid Applied to Foundation Reinforcement of Port Storage Yard
Fiberglass Geogrid Applied to Foundation Reinforcement of Port Storage Yard
Project Background
This project is a new bulk cargo storage yard in the port area. The site was originally a tidal flat reclamation zone with soft soil layers and high compressibility. Subject to long-term static heavy loads from containers and bulk materials, the yard is prone to uneven settlement and ground cracking. The design adopts the scheme of **cushion + fiberglass geogrid reinforcement layer** to improve foundation bearing capacity, reduce differential settlement and prevent yard surface cracking, so as to meet the requirements of container stacking and forklift operation.
Note: Woven geotextile for filtration is often used together for soft soil reinforcement of port yards. The fiberglass geogrid mainly provides reinforcement and restrains lateral deformation.
Specification and Quantity
Type: Fiberglass Geogrid
Specification: Tensile strength 120kN/m, elongation ≤3%, excellent creep resistance
Net laying area: 126,000 ㎡
Loss factor for sectional overlapping and edge corners of the yard: 12%
Total purchasing quantity: 141,120 ㎡
Functions
✅Foundation reinforcement and lateral confinement: Restrain lateral extrusion of soft soil and improve the bearing capacity of composite foundation.
✅ Stress homogenization: Evenly distribute the upper stacking load to the underlying soft soil layer and reduce differential settlement.
✅ Crack resistance: Inhibit cracking of the upper hardened surface caused by settlement difference.
✅ Creep resistance: Fiberglass features low elongation and low creep, suitable for long-term constant stacking load conditions in ports.
Construction Parameters
Subbase: The crushed stone cushion shall be leveled and compacted to meet the compaction standard, with no sharp stones on the surface.
Laying direction: The main strength direction of the geogrid shall be parallel to the main load direction of the yard.
Overlap: Overlap width ≥15 cm; overlapping positions shall be staggered and not arranged on the same section.
Fixation: Fixed with U-shaped anchor nails at a spacing of 2.0 m × 2.0 m.
Upper backfill: The upper crushed stone shall be backfilled promptly after geogrid laying. Heavy machinery is prohibited from sudden braking or turning directly on the geogrid.
Backfill and compaction shall be carried out in layers, and the thickness of each single fill layer shall comply with specifications.