Municipal Soft Soil Subgrade New Road Project

2026/06/21 11:24

Municipal Soft Soil Subgrade New Road Project

1. Project Overview

New municipal trunk road in Jiangsu coastal city, total length 5.8km. The whole line is coastal mucky soft soil, low bearing capacity, large compression deformation; traditional deep soil replacement would generate massive waste soil and delay construction period.

2. Geotextile Application Details

  • Material: 500g/m² high-strength filament reinforcing geotextile

  • Scheme: Single layer geotextile laid on cleared subgrade surface, covered with 25cm gravel filling layer

  • Construction control: No excessive tension during laying, reserved shrinkage allowance; layered compaction with light roller first

3. Core Functions Played

  1. Load dispersion: Improve overall bearing capacity of soft foundation

  2. Accelerate consolidation: Drain pore water of soft soil to shorten foundation stabilization time

  3. Anti-puncture: Buffer sharp gravel to avoid fabric tearing

4. Acceptance & Operation Effect

  • Subgrade bearing capacity increased from 55kPa to 110kPa, meeting highway design standard

  • Total settlement reduced by 42% compared with pure filling scheme

  • Construction period shortened by 22 days, reduce waste soil transportation and disposal cost